Nuclear Power Projects - Commissioning



          Prototype Fast Breeder Reactor (PFBR)








































          Commissioning activities are in progress at 500 MWe   Decoupling and recoupling of Large Rotatable Plug
          Prototype  Fast  Breeder  Reactor (PFBR). Clearance   (LRP)  bearing is planned  for investigation  of high
          for receipt, handling and storage of 42 numbers of   torque observed during trial rotation of LRP. AERB
          fresh fuel sub-assemblies (FSA) at Fuel Building (FB)   Site Observers Team  (SOT)  deputed at  Kalpakkam
          was issued on June 28, 2019  after  detailed safety   Site has been independently observing  ongoing
          review and assessment of the application along with   commissioning  activities at  PFBR with  respect to
          the supporting documents.                           regulatory safety aspects.