for design, construction and operation of NPPs. The  Table 3.2:  Regulatory  Inspections of Operating
               implementation of QA programme applicable to the  Nuclear Facilities
               activities of NPCIL HQ was also verified during this
               inspection with reference to AERB Safety Code on          Facilities           No. of Inspections
               ‘Quality Assurance in Nuclear Power Plants’.
                                                                                   Operating NPP
              The functions and activities performed by Directorate
           of Technical, Technical-LWR, Projects, Operations      TAPS-1&2                             6
           and Quality Assurance (QA) were focussed during the    TAPS-3&4                             6
           inspection in addition to other supporting directorates.
                                                                  RAPS-1&2                             4
              The  number  of  inspections  conducted  in  each  of
           Nuclear Facilities (Under construction & Commissioning),   RAPS-3&4                         5
           Operating NPP and Industrial & Fuel Cycle Facilities are   RAPS-5&6                         4
           given in Table 3.1, 3.2 and 3.3 respectively           MAPS-1&2                             5

           Table 3.1: Regulatory Inspections of Nuclear           NAPS-1&2                             6
           Facilities under Construction and Commissioning        KAPS-1&2                             3


                   Project             No. of Inspections         KGS-1&2                             10
            GHAVP-1&2                           2                 KGS-3&4                              4
            KKNPP-3&4                           4                 KKNPP-1&2                            4
            KKNPP-5&6                           2                                 IGCAR Facilities
            KAPP-3&4                            3                 FBTR, KAMINI, IFSB                   2
            RAPP-7&8                            5                 CORAL                                2
            PFBR                                5                 RML                                  1
            DFRP                                2
            FRFCF                               2                 RCL                                  1
            NFC-Kota                            2                 FRTG                                 1
            Total                              27                  Total                              64