A.3  Pressurized Heavy Water Reactor (PHWR)        Subsequently,  NPCIL  application  seeking
                                                               clearance  for  'Initial  Fuel  Loading'  (IFL),  part
                  (i)     KAPP-3&4 and RAPP-7&8                borated heavy water (65 Te) addition to storage,
                                                               cooling and moderator systems for ushing and
                        Safety Review of KAPP-3                addition of Heavy Water to PHT into the reactor
                                                               of KAPP-3 was reviewed and Clearance for the
                       Safety review of various submissions for the   IFL part of the application was issued on February
                  twin  units  of  700  MWe  PHWRs  at  Kakrapar,   28, 2020. Clearance for addition of 65Te Heavy
                  Gujarat (KAPP-3&4) and Rawatbhata, Rajasthan   water  to  Moderator  systems  and  addition  of
                  (RAPP-7&8) was in progress. Review Groups in   Heavy  water  to  PHT  systems  of  KAPP-3  was
                  AERB  (i.e.  In-House  Working  Groups,  Task   granted on March 18, 2020 with a regulatory hold
                  Force,  PDSC)  are  progressively  reviewing   point (RHP) for addition of Heavy water to PHT.
                  relevant  submissions  on  Safety  analyses,  and   After  review  of  NPCIL  submissions  towards
                  reports  like  Stress  analysis,  Environmental   clearing  regulatory  hold  point,  permission  for
                  Qualication (EQ), Independent Verication and   Heavy water addition to PHT system was granted
                  Validation (IV&V), Commissioning Procedures,   on  April  06,  2020.  KAPP-3  was  also  granted
                  Technical  Specications  for  Operation,  KAPP-3   Licence under the Factories Act, 1948.
                  applications for various stages of commissioning
                  & related submissions including Commissioning     NPCIL application seeking Authorization of
                  reports. Majority of the safety review for KAPP-  KAPP-3  for  Bulk  addition  of  heavy  water  to
                  3&4  was  conducted  by  AERB  in-house  review   moderator system with minimum specied boron
                  groups.                                      level in heavy water to prevent reactor criticality,
                                                               First Approach to Criticality (FAC), Low Power
                       After completion of Primary Heat Transport   Reactor  Physics  Tests  &  Experiments  was
                  (PHT) System, Hot Conditioning and Light Water   reviewed  and  after  approval  by  the  Board  of
                  Commissioning  (LWC)  of  KAPP-3,  and       AERB,  permission  for  bulk  addition  of  Heavy
                  satisfactory safety review of NPCIL application,   water  to  Moderator  System  of  KAPP-3  was
                  test  results  and  associated  submissions,  AERB   granted  on  July  07,  2020.  Subsequently,
                  issued  permission  for  draining  of  light  water   permission  for  FAC  and  low  power  reactor
                  from  PHT  system  on  December  16,  2019  and   physics experiments was granted on July 17, 2020.
                  draining of light water from Moderator system on   KAPP-3 achieved Criticality on July 22, 2020.
                  January 13, 2020.